Hybrid Solar Air Conditioner

KF-70GWS 24000 BTU hybrid solar air conditioner, on grid wall split, photovoltaic DC input plus mains AC, indoor head and outdoor condenser, panels and battery set, flare line set, remote control
Send Inquiry
Description
KF-70GWS  /  24,000 BTU  /  on grid hybrid  /  PV plus mains
Buy The Load, Not The Model: A 24,000 BTU Hybrid Is Chosen By The Building
Two buildings can both want 24,000 BTU and still need completely different systems. One runs six hours a day and dies at sunset; the other runs fourteen and only matters after dark. This page works through the five building types that buy this size most often, then shows the array, bank, wiring and commissioning each one ends up with.
Model KF-70GWS  ·  24,000 BTU nominal  ·  about 7.0 kW cooling class  ·  wall split  ·  photovoltaic DC in, mains AC in
24,000
BTU nominal, about 7.0 kW
5
building types covered below
2
power sources, no switch-over
2 x 40 A
DC breakers on array and bank

A 24,000 BTU split is the size where buyers stop asking what the unit costs and start asking what the building costs. At 12,000 BTU the roof is a nice extra. At 24,000 BTU the roof, the bank and the cable run are the project, and the head is the part you fit at the end.

So this page is organised by building rather than by feature. Each case states the load honestly, says what the array has to deliver, and says where the money actually goes. Where a number depends on the site, it is marked as a build value instead of an invented one.

CASE 01

The shop that opens at eight and closes at nine

Retail, 60 to 90 square metres, glazed front, 12 to 14 hours of running
KF-70GWS indoor head above the shelving of a small grocery shop
CASE 01 / RETAIL

Steady load, glazed front, no tolerance for a warm afternoon

A grocery or household goods shop is a bad candidate for an undersized unit and a good candidate for hybrid. The load is steady rather than peaky: doors open all day, the glazing gains heat from ten in the morning, and the shelves hold that heat. An 18,000 BTU unit will cool it at seven in the morning and lose the argument by two in the afternoon.

Two habits make the shop case work. First, mount the head high on the back wall so the throw reaches the counter instead of dumping cold air on the first shelf it meets. Second, let the array run the unit directly while the sun is up, and keep the bank out of the daytime circuit. A shop that sells drinks and dairy cannot afford a bank that is already flat at opening time.

Most shops in this size class end up with four to six panels and a 24 V bank, with the grid covering the evening close-down. That is a planning figure, not a specification: the panel count follows the daily kilowatt-hours, which follow the door count and the glazing.

Shop load profile: 12 to 14 hours a day, highest between 13:00 and 17:00 when the front glass is fully lit.
CASE 02 / CLINIC

Long hours, moderate load, zero tolerance for a stoppage

A clinic waiting area is the case where the system has to be boring. Nobody thanks you for cooling that works; everybody notices when it stops. The load is moderate, the hours are long, and the room is full of people who are already uncomfortable.

This is where the hybrid input earns its place. The unit takes photovoltaic DC when the roof is producing and mains AC when it is not, without a transfer switch and without a second indoor unit. A cloud passes, the compressor keeps running. The mains meter simply starts turning.

The specification detail that matters here is not capacity but stability: one controller deciding between sources, two 40 A DC breakers so either leg can be isolated, and a vacuum and leak test done properly, because a clinic will not tolerate a re-gas visit in three months.

KF-70GWS indoor head on the wall of a clinic waiting area
Critical-load rooms usually keep the mains connected as the fallback leg. The PV input reduces the bill; it is not asked to carry the room alone.
KF-70GWS indoor head in an open-plan office with west glazing at sunset
CASE 03 / OFFICE

Same floor area, different load: the glass decides

An open-plan office is the case that punishes a floor-area rule of thumb. Two offices of the same size can differ by a third of their load depending on which way the glass faces. A west elevation in the afternoon is not a glazing detail, it is the dominant load in the room.

For a west-facing floor, 24,000 BTU buys comfort rather than luxury, and the honest advice is to shade the glass before buying a bigger unit. Internal blinds, an external screen or a film on the pane will do more per dollar than another 6,000 BTU. Once the glass is handled, the unit holds the room comfortably and the array has a load it can actually follow.

Where the office runs to six or seven in the evening, the bank does the last two hours. That is a smaller bank than most buyers expect, and the table in CASE 05 shows why: two hours of evening load is not the same purchase as eight.

A west facade can add a third to the sensible load in the late afternoon. Shade first, then size the unit.
CASE 04 / RESTAURANT

Two loads in one room: seating and a kitchen that never stops

A restaurant is two loads in one room. The dining area is ordinary; the kitchen is a heat engine, and the extract hood only removes part of it. If the head is mounted where it can see the pass-through, it will spend the evening chasing kitchen heat that was never in the cooling calculation.

The practical fix is placement rather than capacity: keep the head over the seating, keep the return path clear, and let the kitchen have its own extract and make-up air. A 24,000 BTU unit that is positioned correctly will out-cool a 30,000 BTU unit aimed at an open kitchen door.

Restaurants also run latest. The evening is the money hour, which makes the bank the deciding purchase: four hours of cover through a dinner service is the usual target, and the array has to be sized for the daytime load plus whatever the bank needs to be refilled before service.

KF-70GWS indoor head above the banquette of a small restaurant
Dinner service is the peak. Size the bank to cover the trading hours, not the whole day.
CASE 05

The bedroom that only needs the night

Small villa or guest room, evening and night running, four to eight hours of cover
Bank class (planning)Evening and night coverTypical setting
Smallabout 2 to 3 hours of full loadGuest room, short evening use, mains tops up
Mediumabout 4 to 5 hoursBedroom through the night in a mild climate
Largeabout 6 to 8 hoursTwo rooms, or a hot night with a high setpoint margin
KF-70GWS indoor head and outdoor condenser photographed on a dark background
CASE 05 / NIGHT LOAD

The purchase that decides the night is the bank, not the roof

Here the arithmetic flips. A bedroom is used when the array is asleep, so the array is not the main purchase; the bank is. Buyers who quote a panel count first usually end up with a roof full of panels and a room that goes warm at eleven at night.

The useful question is not how many kilowatt-hours the bank holds, but how many hours the room has to be held at setpoint with the compressor cycling. A 24,000 BTU inverter head in a well-insulated bedroom draws a fraction of its rated input once the room is down, so the honest way to size the bank is to measure the average draw over a night rather than multiply the nameplate figure by eight.

The table below is a planning aid, not a quotation. Real hours depend on insulation, outdoor night temperature, door openings and how far the setpoint sits below ambient.

Battery chemistry, voltage and capacity are confirmed per order. The hours above are a planning range, not a guarantee.
CASE 06 / SITE OFFICE

A metal box in the sun, and a shift that starts at 45 degrees

A container site office is the least forgiving installation in this list. The walls are 50 mm of sandwich panel, the roof is steel, the windows are small, and the unit is asked to pull a metal box down from 45 degrees at the start of every shift.

Two details separate a working installation from a complaint. The first is shading: if the container sits in full sun, no split unit wins, so a simple shade net over the roof does more than a bigger machine. The second is filtration and service access, because a site office collects dust and a blocked coil turns a 24,000 BTU unit into a 15,000 BTU unit within a season.

Where mains is unreliable, the hybrid input is the whole reason to buy this model. The array keeps the compressor alive through the working day, the mains covers the evening, and the bank is optional rather than mandatory.

KF-70GWS indoor head inside a converted container site office
Roof shading and coil cleaning are part of the specification here, not after-sales advice.
Building typeRunning hoursArray implication (planning)
Bedroom, evening only4 to 8Small array or none; bank carries the load
Shop, 12 to 14 hours12 to 14Largest array in this list; direct daytime drive
Clinic waiting area10 to 12Medium array, mains kept as the fallback leg
Open-plan office8 to 10Medium array, west glazing shaded first
Restaurant10 to 12Medium array plus four hours of bank for service
Two photovoltaic panels mounted on a corrugated metal roof
CASE 07 / ARRAY

The roof has to match the hours, not the model number

This is the part buyers underestimate. 24,000 BTU is roughly 7.0 kW of cooling, and the electrical input that produces it is not a small number once the compressor is at full speed. The array does not have to cover the peak; it has to cover the daily energy, which is a different and usually smaller figure.

The method is three steps and no software. Take the hours the building actually runs. Take the average input over those hours, not the nameplate. Multiply, add a tenth for losses in the controller and cabling, and you have the daily kilowatt-hours the roof must deliver. Panel count then follows from local yield per panel, which depends on latitude, tilt and shading.

Two panels are shown in the photograph because that is a common starting point for a light-use room, not because the model carries a fixed number. On a shop running fourteen hours, the same unit needs a larger array; on a bedroom it may need none at all if the bank is charged from the mains overnight.

Panel wattage, tilt and mounting hardware are quoted per site. The unit accepts a photovoltaic DC input; it does not ship with a fixed panel count.
ItemShips withDecided on site
Indoor headWall plate, remote, drain hoseMounting height and throw direction
Outdoor condenserBase feet, capped valvesBracket or pad, clearance to the wall
Line setNot includedRun length, flare sizes, insulation
ArrayNot includedPanel count, tilt, cable route
BankNot includedVoltage, capacity, hours of cover
CASE 08 / WHAT SHIPS

Four items, and only one of them is decided in the factory

What arrives is a set, and it is worth knowing what is in each carton before the installer arrives, because site delays usually come from one missing bracket rather than a missing machine.

The indoor head ships with its wall plate, remote control and drain hose. The outdoor condenser ships on its base feet with the service valves capped. The line set is a separate item and is cut to the run on site, which is why the run length has to be known before the order is confirmed rather than after.

Panels and bank are quoted separately because they are site decisions. A buyer who already owns a photovoltaic array can use it, provided the DC input window matches; a buyer who does not should decide the array size before the unit ships, not after.

Indoor head, outdoor condenser and two photovoltaic panels standing in a row
Line set, array and bank are quoted per project. Nothing in this list is silently included in the unit price.
LegRuns betweenProtectionNote
Array DCPanels to controller40 A DC breakerPanels wired in groups, all facing the sun
Battery DCBank to controller40 A DC breaker4 mm squared minimum on this platform
AC feedMains to unitDedicated circuit breakerNot shared with other heavy loads
Technicians lifting the outdoor condenser onto a wall bracket
CASE 09 / WIRING

One controller, three cable sets, two DC breakers

The electrical side is where a good unit gets a bad reputation. There is one controller, and three cable sets meet it: the array DC, the battery DC, and the AC side that feeds the head. Each leg gets its own protection, and the two DC legs each need a 40 A breaker so that either can be isolated for service without shutting the room down.

Cable size matters more than buyers expect. The controller to battery run is specified at 4 mm squared on this platform, and undersizing it turns a working system into one that trips under load and gets blamed on the machine. Every DC cable should be labelled at both ends before the trunking goes on, because the next person to open that box will not be the person who wired it.

The AC side is a dedicated circuit. Sharing it with a water heater is the most common cause of a nuisance trip in the first week, and it is entirely avoidable at the planning stage.

Breaker ratings and cable sizes above follow the installation guide supplied with the unit. Site codes take precedence where they are stricter.
CASE 10

Eight steps, and the order is not negotiable

A 24,000 BTU split is heavy enough that sequence matters more than speed

Every failed installation we have seen failed in the same three places: the wall plate went up without checking the fall, the line set was flared after it was already through the wall, and the unit was started before the vacuum was finished. The sequence below is deliberately boring.

Two people are required for this size. The indoor head is long and the outdoor unit is not a one-person lift above shoulder height.

StepWhat happensWhat is checked before moving on
01Survey and mark the head and condenser positionsThrow reaches the far wall; condenser clearance both sides
02Fix the wall plate with four expansion screwsPlate level; fall to the drain side confirmed
03Drill the wall penetration and fit the sleeveSleeve slopes outwards so condensate cannot run back
04Cut, flare and connect the line setBoth flares inspected before tightening, not after
05Hang the head, connect drain and wiringHead seated on the plate; drain falls continuously
06Mount the condenser on bracket or pad, connect valvesUnit level; service valves accessible without removing panels
07Run array to controller, controller to bank, AC to unitTwo 40 A DC breakers fitted; every DC cable labelled
08Evacuate, open valves, leak test, first run on both sourcesVacuum held; no pressure drop; both inputs verified
CheckTargetWhy it matters
Vacuum holdHolds at the required level after isolationMoisture in the circuit turns to acid in the oil
Leak testNo bubble growth at either flare or valve capA slow leak is the most common first-year failure
Run on PV onlyCompressor starts and holds setpointProves the DC leg and the controller logic
Run on mains onlyCompressor starts with the array isolatedProves the AC leg independently
Source changeoverNo trip when the array drops outClouds must not restart the room
DrainWater reaches the outside without poolingThe second most common call-out after leaks
CASE 12 / SERVICE AND SHIPPING

The second season is the only review that counts

The second season is the honest test. A unit that was installed with labelled cables, accessible valves and a clean coil takes an hour to service. A unit that was installed for the photograph takes half a day, and that cost lands on the buyer rather than the installer.

For spares, the list that actually moves is short: flare gaskets, valve caps, a remote control, the drain hose and the fan capacitor. Keeping those on the shelf turns a two-week wait into an afternoon. Everything else is a factory order.

Shipping follows the same logic. The head and the condenser travel on separate pallets, panels travel upright and strapped, and the line set is coiled separately so it is not crushed under a carton. Mixed containers with other models from the range are normal, and the loading plan is agreed when the order is confirmed.

Outdoor condenser and cartons on pallets at the doors of a shipping container
Packing quantities and container loading are confirmed per order. Panels and bank are shipped as separate items.

THREE SIZES
One architecture, three capacities

The same hybrid platform is built in three capacities. The difference is not only the cooling output: the array and the bank scale with the size, and the buyer who starts at 24,000 BTU is usually buying for a room that will not be reconfigured later.

ModelCapacityTypical roomWhat changes at this size
KF-35GWS12,000 BTU, about 3.5 kWBedroom or small officeOne panel pair is often enough; bank optional
KF-50GWS18,000 BTU, about 5.3 kWShop or mid-size officeArray becomes the main purchase
KF-70GWS24,000 BTU, about 7.0 kWOpen-plan, restaurant, clinicArray plus bank; wiring protection matters

WHAT GOES WRONG
Five mistakes that cost more than the unit

These are the five we meet most often on 24,000 BTU projects. None of them is a manufacturing fault, and all of them are decided before the unit is switched on.

1
Sizing by floor area alone
Two rooms of the same area, one north-facing and one west-facing, do not need the same capacity. Ask which way the glass faces before the number is fixed.
2
Buying the array before the hours
The roof follows the daily energy, not the model number. Estimating panel count from the unit capacity is guessing with extra steps.
3
Treating the bank as a battery for the unit
The bank covers the hours the building uses after sunset. If the building closes at six, the bank is small; if it trades until eleven, it is not.
4
Skipping the isolation test
A hybrid that is proved on both sources separately will fail in a way you can diagnose. One that is proved only on mains will hide a DC fault until the first cloudy day.
5
Leaving the DC cables unlabelled
The next technician will not be the one who wired it. Ten minutes with a marker prevents an hour of guessing and one wrong breaker operation.

QUESTIONS
What buyers ask before the quotation

Does the price include panels and a battery?
No. The unit price covers the indoor head, the outdoor condenser, the wall plate, the remote and the drain hose. Panels, bank, line set and mounting hardware are quoted against the site, because they depend on the run length, the hours and the local yield.
Can I buy the air conditioner now and add the array later?
Yes, and that is a common order. The unit runs on mains alone until the array is connected. The DC input is capped and protected internally, so an array added later does not require a different indoor unit.
What happens at night if I have no battery?
The unit switches to mains and keeps running. The bank is an economic decision about the evening bill, not a requirement for operation. A bedroom with no bank still cools through the night on mains.
How many hours will it run on a battery?
Work it out in three steps: average input while the room is at setpoint, number of hours you need, and a tenth for losses. A 24,000 BTU inverter head holds a bedroom at a fraction of its rated input, so the honest figure comes from that average, not from the nameplate multiplied by eight.
The mains here is unreliable. Does that change the specification?
It changes two things: the bank becomes mandatory rather than optional, and the controller must be configured so that a mains dropout does not restart the compressor. This is a commissioning setting, not an extra part.
I already have solar panels. Can I use them?
Usually yes, provided the array voltage and current window matches the DC input of the unit. Panels wired for a different inverter may need to be reconfigured into groups. Send the array specification with the enquiry and it can be checked before the order.
Is 24,000 BTU too much for a shop of about 60 square metres?
It is the right size for a glazed shop of that area with a 12 to 14 hour trading day, and oversized for a shaded one. The head modulates, so mild oversizing costs less than undersizing, but the glazing and the door traffic decide more than the floor area.
How does it ship?
Head and condenser on separate pallets, panels upright and strapped, line set coiled separately, bank as a separate item. Mixed containers with other models are normal and the loading plan is agreed when the order is confirmed.

SPECIFICATION
KF-70GWS at a glance

Fixed values are stated. Anything that follows the build is marked, because a unit sold with an array and a bank is configured per project, not pulled off a shelf.

ItemValue
ModelKF-70GWS
TypeWall-mounted split, hybrid photovoltaic and mains input
Nominal capacity24,000 BTU per hour, about 7.0 kW cooling class
Power sourcesPhotovoltaic DC input plus mains AC input
Indoor unitWall head with remote control and adjustable louvre
Outdoor unitSingle-fan condenser, service valves on the side panel
RefrigerantType and charge set with the build
Rated currentConfirmed on the order confirmation
Line connectionsTwo flare connections; line set supplied per project
DC protection40 A breaker on the array leg and 40 A on the bank leg
Controller to bank cable4 mm squared minimum on this platform
Wall plateFour expansion screws, supplied
DrainHose supplied; fall to the outside required
DimensionsConfirmed on the order confirmation
Net and gross weightConfirmed on the order confirmation
PackingHead and condenser on separate pallets
CertificationCE for the unit as shipped
BrandingJUKA or private label, confirmed at order
Rows marked "confirmed on the order confirmation" are not omissions. Refrigerant charge, rated current, dimensions and weights change with the array and bank configuration, and stating a single figure for all builds would be wrong for most of them.
THE FACTORY

Hangzhou, where the panel and the compressor are specified in the same room

Juka has been building solar cold chain and solar air conditioning equipment since 2015, on a site in Hangzhou where the refrigeration side and the power side are engineered together rather than assembled from two catalogues. That matters most at 24,000 BTU, where the array, the bank and the compressor have to agree on a duty cycle.

Units ship to Ghana, Gabon, Cameroon, Nigeria, Kazakhstan and India, mostly to distributors and installers who specify the array themselves and need the unit to behave predictably on the DC leg. The test bench exists for that reason: every unit is evacuated, charged by weight and run on both sources before it is packed.

2015
building solar cooling since
2 + 17
invention and utility patents
CE
unit certification as shipped
Technicians testing a unit on the production line
ON THE LINE

What the bench catches before packing

Evacuation before charge, charge by weight rather than by gauge, a run on both sources, and a final inspection that is separate from the assembly team. The last point is the one that changes outcomes: the person who signs off is not the person who built it.

Assembly area at the Hangzhou factory
Coil and cabinet assembly on the production line

Documents travel with the shipment: the CE declaration for the unit, the test record from the bench, and the packing list that matches the pallet markings. If a project needs a certificate of origin or a specific invoice format, say so when the order is placed rather than after the container is sealed.

CE declaration for the solar air conditioner
CE schedule of the certified models
Utility model patent certificate

OEM, ODM and local assembly

✓  Private label on the head, the condenser and the cartons

✓  Control logic and remote layout adjusted for a distributor programme

✓  Panel and bank bundles quoted as a set with the unit

✓  Spare parts kit packed with the first container

✓  Documentation in the buyer language on request

Hot Tags: hybrid solar air conditioner, China hybrid solar air conditioner manufacturers, suppliers, factory